125 London Wall

Scope of work

Project Jigsaw. The works were carried out on levels 4, 6 & 7. The works included new lighting, new small power. All new luminaires and lighting controls were installed. The power was completely rewired and serves under floor track, desk harness umbilical's and floor boxes. A satellite equipment room was also constructed on level 4. Fire suppression and VESDA systems were also installed. Extensive modifications were carried out on the existing Fire detection and alarm system. The building was fully occupied throughout the works. Planned shutdowns were implemented to integrate new critical systems.

Client:
A major American Commercial Bank

Main Contractor:
Overbury

Consultant:
The Anslow Partnership

Value:
£434, 000